§ 96.44 PRE-EXCAVATION FACILITIES LOCATION.
   In addition to complying with the requirements of M.S. §§ 216D.01 through 216D.09 (“One Call Excavation Notice System”) before the start date of any right-of-way excavation, each registrant who has facilities or equipment in the area to be excavated shall:
   (A)   Mark the horizontal and vertical placement of all such facilities; and
   (B)   Notify and work closely with the excavation contractor to establish the exact location of its facilities and the best procedure for excavation, if its facilities are less than 20 inches below a concrete or asphalt surface.
(Ord. 85, 6th Series, passed 3-3-2015)