921.18 BTM GENERATORS.
   (a)   Subject to meeting all technical, safety, construction, interconnection or other requirements imposed by Municipality, as well as paying any applicable rates, fees or charges pursuant to approved rates and tariffs, Municipality will permit retail customers to interconnect BTM Generators through their existing interconnection to the Municipal electric distribution system and to utilize energy generated thereby.
   (b)   The Behind-the-Meter (BTM) Generator Policy & Procedures attached to Ordinance 04-23 and made a part of this section are hereby adopted and shall be applicable to all BTM Generators as of the effective date of this section.
   (c)   The Schedule “SPP” - Small Power Production electric rate schedule attached to Ordinance 04-23 and made a part of this section is hereby adopted and shall be applicable to all energy supplied by BTM Generators as of the effective date of this section.
   (d)   Application for Interconnection and Interconnection Agreement between this Municipality and a customer who desires to interconnect a BTM Generator to the Municipal electric utility system, substantially in the forms attached to Ordinance 04-23 as Exhibits 1 and 2, respectively, are hereby approved.
   (e)   The Director of Public Service and Safety is authorized to review and approve or take such other action as necessary on any Application for Interconnection and Interconnection Agreement between this Municipality and a customer of the Municipal Utility.
(Ord. 04-23. Passed 2-27-23.)