905.06 BUILDING PERMIT REQUIREMENTS.
   No building permit shall be issued by the Building Official unless and until the Service Director has examined the proposed building site and the proposed plans to determine if the applicant proposes to provide a satisfactory culvert or drain under the driveway of the premises and adequate lot drainage.
   Upon completion of such examination the Service Director shall notify immediately the Building Official and the builder of his findings and recommendations.
   No building permit shall be issued to any applicant until the recommendations of the Service Director are complied with.
   No trucks or materials of any builder shall be permitted to have access to a proposed building site until all the provisions of this section have been complied with.
(Ord. 1962-20. Passed 7-23-62.)