(a) Request for Inspection. It shall be the responsibility of the person to whom the plumbing permit has been issued to give sufficient advance notice to the Building Inspector when plumbing work is ready for testing or inspection. No work shall be covered or concealed without specific authorization to do so from the Building Inspector.
(b) Preliminary Tests. The person to whom the permit is issued and who is requesting the inspection shall conduct preliminary tests in order to make certain that the work will stand the prescribed test before making the request required in subsection (a) hereof.
(c) Retesting and Reinspection. If the Building Inspector finds that the work does not pass the test or inspection, the necessary corrections shall be made and the work shall then be resubmitted for retesting or reinspection.
(d) Responsibility of Installer. The equipment, material, power and labor necessary for inspections or tests shall be furnished by the installer who shall perform the tests.
(Ord. 1992-101. Passed 1-14-92.)