(A) The Building Commissioner shall be responsible for the completion of all required inspections which shall be indicated on the building permit card.
(B) The permittee shall notify the Department and schedule an inspection when work, for which an inspection is required or requested by the Building Commissioner, is complete, and such notice shall be given as follows:
(l) Four hours prior to the earliest time an inspection is requested for footers, foundations or concrete slabs.
(2) For all other inspections, notice must be provided not less than 24 hours before an inspection is requested.
(C) The Department shall endeavor to schedule all inspections as requested; however, priority is given to inspections which involve an immediate life safety issue and on a first call-in basis.
(D) If a footer, foundation or slab inspection has not been completed within one hour of the time set for inspection by the Department, the permittee may pour concrete and continue work on the footer, foundation or slab provided the work has been completed in compliance with applicable law.
(E) The Department may assess a re-inspection fee for the following. The re-inspection fee shall be paid prior to a re-inspection being scheduled.
(l) Requested footer, foundation, or slab inspection not cancelled at least one hour prior to the earliest scheduled time requested for an inspection;
(2) Other requested inspections not cancelled at least three hours prior to the earliest scheduled time requested for an inspection;
(3) Work not completed by the time requested for inspection; or
(4) Work not in compliance with applicable codes.
(F) The Building Commissioner shall note the passing of each inspection, or the deficiencies and/or corrective work required, on the permit card at the time of inspection. A rework is completed and must pass inspection prior to any additional work being completed which would affect the completion of the required inspection.
(Ord. 12-C-91, passed 7-25-91; Am. Ord. 19-C-14, passed 7-29-14)