§ 55.60 CERTIFICATIONS REQUIRED.
   (A)   After completion of the project and before final approval and acceptance can be made, and prior to issuance of any certificate of occupancy, a professionally prepared and certified “As Built” set of plans shall be submitted to the City Engineer for review. These plans shall include all pertinent data relevant to the completed storm drainage system, and shall include:
      (1)   Pipe size and pipe material.
      (2)   Invert elevations
      (3)   Top rim elevations.
      (4)   Lengths of all pipe structures.
      (5)   Data and calculations showing detention basin storage volume.
      (6)   A certified statement on the plans, stating that the completed storm drainage system substantially complies with the construction plans as approved by the Commission.
   (B)   All such submitted plans shall be reviewed for compliance within 30 days after submission to the city. If notice of non-compliance is not given within 30 days of submission of the plans, the plans shall be construed as approved and accepted.
(Ord. 16-C-98, passed 6-9-98; Am. Ord. 22-C-04, passed 11-9-04)