7-1-2: SIDEWALK CONSTRUCTION SPECIFICATIONS:
All sidewalks hereafter constructed within the village on or along the public streets and alleys shall be constructed only in accordance with the following:
   A.   Concrete Requirements: All concrete shall be 6-bag mix using air entrained cement and crushed aggregate; minimum four thousand (4,000) psi twenty eight (28) day strength. Delivery slips shall be available indicating the mix being delivered to the job site. The village reserves the right to conduct any testing it desires and reject any work not in conformance with these standards.
   B.   Depth: All regular walks shall be four inches (4") thick, except at driveways, where sidewalks shall be six inches (6") across approaches.
   C.   Width: Sidewalks shall be four feet (4') in width.
   D.   Dummy Joints: Dummy joints shall be spaced every four feet (4') and shall be three-fourths inch (3/4") to one inch (1") deep.
   E.   Expansion Joints: Expansion joints of one-half inch (1/2") felt shall be placed every fifty feet (50') at the intersection of crosswalks, adjacent to concrete driveways or at any locations otherwise instructed by the village engineer. (2016 Code)