1377.06 APPLICATION PROCEDURES.
   (a)   Soil Disturbing Activities Submitting a Storm Water Pollution Prevention Plan. The applicant shall submit two (2) sets of the SWP3 to the City of Hubbard and two (2) sets of the SWP3 to the Trumbull SWCD as follows:
      (1)    For subdivisions: After the approval of the preliminary plans and with submittal of the improvement plans.
      (2)    For other construction projects: Before issuance of a zoning permit by the Zoning Inspector.
      (3)    For general clearing projects: Prior to issuance of a zoning permit.
   (b)    Soil Disturbing Activities Submitting an Abbreviated Storm Water Pollution Prevention Plan. The applicant shall submit two (2) sets of the Abbreviated SWP3 to the City of Hubbard and two (2) sets of the Abbreviated SWP3 to the Trumbull SWCD as follows:
      (1)    For single family home construction: Before issuance of a zoning permit by the Zoning Inspector.
      (2)    For general clearing projects: Prior to issuance of a zoning permit.
   (c)   The City of Hubbard and the Trumbull SWCD shall review the plans submitted under Section 1377.06(a) or (b) and approve or return for revisions with comments and recommendations for revisions after receipt of the plan. A plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised plan.
   (d)   Soil disturbing activities shall not begin and zoning permits shall not be issued without an approved SWP3 or Abbreviated SWP3.
   (e)   SWP3 for individual sublots in a subdivision will not be approved unless the larger common plan of development or sale containing the sublot is in compliance with this regulation.
   (f)   Approvals issued in accordance with this regulation shall remain valid for one (1) year from the date of approval.
(Ord. 10-09. Passed 5-4-09.)