§ 99.08 REVIEW PROCESS.
   (A)   Upon receipt of the required exhibits, the city shall have ten days to review the site plan, make one of the following decisions and respond to the applicant:
      (1)   Approve the plans as submitted;
      (2)   Grant conditional approval and require the applicant to make changes in order to comply with this chapter or any other specifications; or
      (3)   Deny approval of the site plan as inappropriate with design standards established in this chapter or any other specifications.
   (B)   In instances where minor work within the right-of-way is requested including, but not limited to, sidewalks less than 50 feet in length, curbs less than 50 feet in length, ditches less than 50 feet in length or driveway drainage tiles, the review and response time for the projects may be reduced to three days.
(Ord. 40-2006, passed 10-17-2006)