(A) As work progresses under a permit, the holder thereof or authorized agent shall cause the Zoning Inspector to be notified at the following stages of construction:
(1) Upon completion of the footing and foundation walls;
(2) Upon completion of the rough frame of the building or structure and the electrical wiring; and
(3) Upon total completion of the work authorized by the permit and before occupancy or use.
(B) Should the permit holder fail to comply with all of the terms and provisions of this chapter at any stage of construction, the Zoning Inspector is authorized to revoke and cancel the permit and cause notice of such posting to be considered as service upon and notice to the permit holder of the cancellation and revocation of the permit. No further work shall be undertaken or permitted upon such construction until a new permit is issued for such work.
(Prior Code, Ch. XV, § 15.04) (Ord. 1977-1, passed 10-10-1977; Ord. 2001-1, passed 7-17-2001)