§ 157.327  REGULATIONS.
   The following regulations shall apply to all land uses requiring site plan approval.
   (A)   The Chairperson of the Planning Commission shall not sign the approved site plan until the applicant has submitted three copies of all permits that may be required by the county or the state for the construction of the use, such as but not limited to, permits for on-site wastewater disposal and permits required under the Soil Erosion and Sedimentation Act, Public Act 346 of 1972, and the Wetland Protection Act, Public Act 203 of 1979.
   (B)   The construction of improvements shall not commence for any development that requires a site plan approval until an approved site plan has been signed by the Chairperson of the Planning Commission.
   (C)   The Zoning Administrator shall not issue a zoning permit for any use requiring site plan approval until an approved site plan has been signed by the Chairperson of the Planning Commission.
   (D)   The Building Inspector shall not issue a building permit for any use requiring site plan approval until an approved site plan has been signed by the Chairperson of the Planning Commission.
(Prior Code, Ch. XV, § 12D.13)  (Ord. 2001-1, passed 7-17-2001)