(A) After receiving the Planning Commission’s recommendations on the preliminary plan, the applicant shall submit to the Township Clerk a minimum of ten copies of a final site condominium development plan which complies with the requirements of §§ 157.320, 157.321 and 157.322 of this chapter. The Township Clerk shall forward the copies of the final plan to the Township Board.
(B) The final site condominium project plan submitted by the applicant shall incorporate all of the recommendations, if any, made by the Planning Commission based on its prior review of the preliminary plan. If any of the Planning Commission’s recommendations are not incorporated in the final plan, the applicant shall clearly specify in writing which recommendations have not been incorporated and the reasons why those recommendations have not been incorporated. Except for the changes made to the plan as necessary to incorporate the recommendations of the Planning Commission, the final plan shall otherwise be identical to the preliminary plan that was reviewed by the Planning Commission. Major changes made to the plan other than those necessary to incorporated the recommendations of the Planning Commission shall be reviewed by the Planning Commission and will necessitate a second preliminary review as provided by this subchapter prior to approval of the plan by the Township Board.
(C) After receiving the Planning Commission’s recommendations on the preliminary plan and a final site condominium development plan from the applicant, the Township Board shall proceed to review and may approve, deny or approve with conditions the plan in accordance with the procedures, standards and requirements provided or referenced by this subchapter.
(D) As a condition of approval of a final site condominium project plan, the Township Board may require that a cash deposit, certifies check, irrevocable bank letter of credit or surety bond acceptable to the Board covering the estimated cost of improvements associated with the site condominium project for which approval is sought be deposited with the township as provided by § 16(f) of the Township Rural Zoning Act.
(Ord. 3-2004, passed 8-9-2004)