(A) Construction plans. It shall be the responsibility of the subdivider of every proposed subdivision to have prepared by a registered professional engineer or a registered land surveyor, a complete set of construction plans, including profiles, cross-section, specifications and other supporting data, for the hereinafter required streets, utilities, storm drainage and other facilities. Such construction plans shall be prepared in conjunction with the final preliminary plat. Construction plans are subject to approval by the approving bodies listed in § 156.022 of this chapter and shall be prepared in accordance with the standards or specifications of the respective body.
(B) Engineering plans. Upon completion of the required improvements, one complete copy of as-built engineering plans for each required public improvement shall be filed with the Township Clerk. Other requirements and procedures in the submittal of final plats shall be as provided in § 156.022 of this chapter.
(C) Modifications during construction. All installations and construction shall conform to the approved engineering drawings. However, if the proprietor chooses to make minor modifications in design and/or specifications during construction, he or she shall make such changes at his or her own risk, without any assurance that the township or other public agency will accept the changed facility. It shall be the responsibility of the proprietor/subdivider to notify the appropriate agency of any changes in the approved drawings.
(D) As-built drawings. The proprietor/subdivider shall submit to the Township Board a copy of “as-built” engineering drawings of each of the required improvements that have been completed prior to final plat approval. Each set of drawings shall be certified by the proprietor’s engineer. Similar drawings shall also be submitted of improvements installed under bond or letter of credit, after final plat approval.
(E) Construction schedule. The proprietor shall submit to the Township Board a general schedule of the timing and sequence for the construction of all required improvements prior to final approval of the preliminary plat. The schedule shall meet the procedural requirements and inspection requirements and inspection needs of the township, county and state agencies.
(Prior Code, Ch. XXXIII, § 5.2) (Ord. 2-2004, passed 8-9-2004)