(A) A ready-to-serve charge per premises per quarter as noted in underlying chart. PREMISES is defined as each residential unit and each commercial or industrial facility. If any premises has more than one meter, a ready-to-serve charge shall be assessed on each meter.
Charge 2021 | Charge 2022 | Charge 2023 | Charge 2024 | Charge 2025 |
$66.00 | $67.00 | $68.00 | $69.00 | $71.00 |
(B) In addition, a user fee for each 1,000 gallons of water utilized per quarter as noted in the underlying chart (based on the water meter reading, or if there is no water meter, based on the average water usage for that size of family or type of use within the village).
Per 1,000 2021 | Per 1,000 2022 | Per 1,000 2023 | Per 1,000 2024 | Per 1,000 2025 |
$3.50 | $3.60 | $3.70 | $3.80 | $3.90 |
(C) The sewer use charges shall be reviewed annually by the Village Council.
(Prior Code, § 544.04) (Ord. 2016-001, passed 3-7-2016; Am. Ord. -, passed 6-5-2017; Am. Ord. 2021-001, passed 4-12-2021)