§ 55.19 PRE-CONSTRUCTION FACILITIES LOCATION.
   (A)   Before commencing major construction, each registrant who has facilities located in the proposed construction area shall mark the horizontal and vertical placement of all of its facilities, in conformance with the marking guidelines of the Utility Location and Coordination Council of the American Public Works Association.
   (B)   Any registrant whose facilities are less than 20 inches below a paved surface shall notify and work closely with any other registrant proposing to construct equipment in the construction area to minimize the potential damage or disruption from construction.
(Ord. O-2000-29, passed 7-19-00; Am. Ord. O-2020-14, passed 10-7-20)