§ 157.202 SUBMITTAL OF AS BUILT PLANS.
   Upon completion of the installation of required improvements as shown on the approved final site plan, the property owner shall submit to the Zoning Official two copies of an “as built” site plan, certified by an engineer or architect, at least one week prior to the final inspection leading to a certificate of zoning compliance. A certificate of zoning compliance shall be withheld by the Zoning Official in any case where the final site plan and major conditions as approved by the Planning Commission and/or Zoning Commission, as required, have not been complied with. Any minor variations may be approved by the Zoning Official, and shall be reported to the Planning Commission and/or Zoning Commission, as required, within 30 days after the issuance of a certificate of zoning compliance.
(Ord. 259, passed 10-24-1995; Ord. 339, passed 4-15-2001; Ord. passed 2-1-2012)