§ 51.19 EROSION AND SEDIMENT CONTROL PLAN.
   (A)   The Erosion and Sediment Control Plan shall include:
      (1)   A soil survey map identifying soils, and existing vegetative cover. A soil survey will be available at the city, or the local ASCS office.
      (2)   A sequence of construction of the development site, including stripping and clearing, rough grading, construction of utilities, infrastructure, and buildings, and final grading and landscaping. Sequencing shall identify the expected date on which clearing will begin, the estimated duration of exposure of cleared areas, and the sequence of clearing, installation of temporary erosion and sediment measures, and establishment of permanent vegetation.
      (3)   All erosion and sediment control measures necessary to meet the objectives of this chapter throughout all phases of construction and permanently, after completion of development of the site. Depending upon the complexity of the project, the drafting of intermediate plans may be required at the close of each season.
      (4)   Seeding mixtures and rates, types of sod, method of seedbed preparation, expected seeding dates, type and rate of lime and fertilizer application, and kind and quantity of mulching for both temporary and permanent vegetative control measures.
      (5)   Provisions for maintenance of control facilities, including easements and estimates of the cost of maintenance.
   (B)   Modifications to the plan:
      (1)   Major amendments of the Erosion and Sediment Control Plan shall be submitted to the city or its designated agent and shall be processed and approved, or disapproved, in the same manner as the original plans.
      (2)   Field modifications of a minor nature may be authorized by the city or its designated agent by written authorization to the permittee.
(Ord. 2004-17, passed 11-15-04)