§ 159.23 STABILIZATION OF DENUDED AREAS AND SOIL STOCKPILES.
   (A)   Permanent soil stabilization shall be installed on denuded areas within seven days after final grade is reached on any portion of the site. Application practices include vegetative establishment, mulching, and the early application of gravel base on areas to be paved. Soil stabilization measures should be selected to be appropriated for the time of year, site conditions, and estimated time of use.
   (B)   Temporary soil stabilization shall be required on any denuded area which will not be regraded for longer than 30 days. Temporary soil stabilization shall be applied within seven days after rough grading.
   (C)   Soil stockpiles shall be stabilized or protected with sediment trapping measures to prevent soil loss.
(1982 Code, § 159.23) (Res. 96-20, passed 2-3-1997)