1167.011 COMPLETION OF IMPROVEMENTS.
   Following final approval of a plat for the subdivision of land, or the commencement of the installation of required improvements, after approval of the improvement plans has been granted in accordance with the provisions of Section 1165.05, and prior to the granting of final approval of the subdivision, the allotter must commence with the construction of all underground improvements, as required by this chapter, within one year from the date of final approval or approval of the improvement plans prior to granting a final approval. All underground improvements as required by this chapter, together with the installation of paving and curbs within the subdivision, must be completed within two years following the date of final approval of improvement plans prior to the granting of final approval. Extensions for the aforestated time periods may be granted by Council for good cause shown and must be confirmed by a resolution of Council.
(Ord. 5-1968. Passed 3-26-68.)