(A) Pursuant to I.C. 13-18-27, an MS4-designated entity or other review authority such as SWCD shall make a preliminary determination as to whether the construction plan associated with SWPPP is substantially complete before the end of the tenth working day (for sites with less than five acres of land disturbance) after the day on which the SWPPP is submitted to the review authority or the fourteenth working day (for sites with five acres or larger of land disturbance) after the day on which the SWPPP is submitted to the review authority.
(B) Note that the above time limits only apply to the SWPPP portion of the overall stormwater approval submittal and does not affect any official or non-official approval review timelines set by the County Drainage Board and/or the Surveyor for other aspects of the stormwater approval application.
(Ord. 2023-45, passed 12-12-2023)