§ 70.31 NON-COMPLIANCE.
   (A)   The following conditions or events, as determined by the County Engineer, represent noncompliance with the permit:
      (1)   Permittee’s work is substantially completed but does not fully comply with the applicable standards following notification to permittee and providing 30 days for correction;
      (2)   The term of the permit is expiring and permittee is not making continuing, diligent efforts to complete the work; or
      (3)   Where a condition exists related to the permit work that, in the County Engineer’s opinion, creates an unsafe condition or a hazard and permittee has not corrected the condition after being notified and provided the opportunity to resolve the condition.
   (B)   A permit time extension shall satisfy the non-compliant conditions or events represented under divisions (A)(1) or (2) above.
   (C)   The County Engineer is authorized to issue a stop work order for work under any permit until any condition under division (A)(3) above is resolved.
   (D)   Upon a condition or event of non-compliance, the County Engineer may notify the permit bond holder that a claim is pending under the permit bond to complete the work. The County Engineer thereafter may take such actions as he considers prudent to cause the work to be completed.
(Ord. 2023-11, passed 3-14-2023)