§ 152.093 REVIEW OF INDIVIDUAL LOTS, PARCELS.
   (A)   For individual lots disturbing less than one acre, developed within a larger permitted project, or larger than one acre individual parcels that are not part of a larger permitted project, a formal review and issuance of an individual lot plot plan clean water permit will be required before a building permit can be issued. If part of a larger permitted project, all stormwater management measures necessary to comply with this chapter must be implemented in accordance with the permitted plan for the larger project. All individual lot plot plans must also receive the County Surveyor’s approval.
   (B)   The following information must be submitted to the county for review and acceptance by the individual lot operator, whether owning the property or acting as the agent of the property owner, as part of a request for review and issuance of an individual lot plot plan clean water permit that must be obtained prior to the issuance of a building permit.
      (1)   The individual lot operator must complete an individual lot clean water permit request and pay the applicable fee.
      (2)   A certified site layout for the subject lot and all adjacent lots showing elevation contours and its source, building pad location, dimensions, elevations, proposed sump pump connections (not to road sub-drains), and the drainage patterns and swales (including side yard swales).
      (3)   Erosion and sediment control plan that, at a minimum, includes the following measures:
         (a)   Installation and maintenance of a stable construction site access;
         (b)   Installation and maintenance of appropriate perimeter erosion and sediment control measures prior to land disturbance;
         (c)   Minimization of sediment discharge and tracking from the lot;
         (d)   Clean up of sediment that is either tracked or washed onto roads. Bulk clearing of sediment shall not include flushing the area with water. Cleared sediment must be redistributed, or disposed of, in a manner that is in compliance with all applicable statutes and rules;
         (e)   Adjacent lots disturbed by an individual lot operator must be repaired and stabilized with temporary or permanent surface stabilization; and
         (f)   Self-monitoring program, including plans and procedures.
      (4)   Name, address, telephone number, and list of qualifications of the trained individual in charge of the mandatory stormwater pollution prevention self-monitoring program for the project site.
   (C)   The individual lot operator is responsible for installation and maintenance of all erosion and sediment control measures until the site is stabilized.
(Ord. 2017-03, passed 1-24-2017)