12-2-15: PUBLIC IMPROVEMENTS TO BE INSTALLED:
The following public improvements must be installed in conformance with plans, specifications and a construction schedule approved by the City. The required improvements must be installed as follows:
   A.   Streets within and adjacent to the subdivision to City standards.
   B.   Sidewalks on both sides of the streets must be installed by the owner of the subdivided property concurrent with installation of streets, curbs, and gutters. Boulevard landscaping and trees, including irrigation, must be installed on public rights-of-way abutting private or public parks, open space, common areas, or other areas intended to be used by the public or common owners must be installed by the owner of the subdivided property concurrent with installation of streets, curbs, and gutters.
   C.   All nonmotorized paths located on public rights-of-way.
   D.   Curb and gutter must be installed on both sides of the streets.
   E.   All stormwater facilities.
   F.   Street name, traffic, and parking control signs must be provided to developer at cost by the City.
   G.   Except as herein provided, new utility distribution lines must be placed underground. Associated equipment, such as pad mounted transformers, may be placed above the surface if required for reasons of convenience, safety, or economy. This subsection does not apply to a main electric feeder line capable of conveying two thousand (2,000) kVA or more.
   H.   Water and wastewater mains, fire hydrants, manholes, stormwater lines, and other necessary appurtenances to serve the subdivision. Water and wastewater mains must be installed to the exterior boundary lines of the subdivided property to allow the future connection of adjacent property. (Ord. 3166, 9-23-2013)