§ 150.01 PERMIT FEES.
   The building permit fee schedule shall be as follows:
Estimated Cost of Construction
Building Permit Fee
Estimated Cost of Construction
Building Permit Fee
$50 to $250
$ 1.50
$251 to $500
$ 5.00
$501 to $1,200
$10.00
$1,201 to $3,000
$15.00
$3,001 to $15,000
$15 for first $3,000 and $2.50 per $1,000 over $3,000
$15,001 to $100,000
$45 for first $15,000 and $2 per $1,000 over $15,000
$100,001 to $500,000
$215 for first $100,000 and $l per $1,000 over $100,000
$500,001 to $1,000,000
$815 for first $500,000 and $.15 per $1,000 over $500,000
Moving building or structure
$10
Fee for zoning amendment
$25
Fee for special exception
$5
Fee for variance
$5
 
(Ord. 920.1, passed - )