A. Short term control measures may include:
1. Regularly scheduled wet suppression;
2. Dust suppressants applied in amounts and rates recommended by the manufacturer and maintained as recommended by the manufacturer;
3. Upwind temporary windbreaks, including fabric fences with the bottom of the fence sufficiently anchored to the ground to prevent material from blowing underneath the fence;
4. Starting construction upwind and stabilizing disturbed areas before disturbing additional areas; and/or
5. Stopping active operations during high wind periods.
B. Long term control measures may include:
1. Site stabilization using dust suppressants applied in amounts and rates recommended by the manufacturer and maintained as recommended by the manufacturer;
2. Reseeding using native grasses;
3. Xeriscaping;
4. Tree planting; and/or
5. Permanent perimeter and interior fencing. (Ord. 352, 2009)