8.28.150: ACTIVE OPERATIONS IN CONSTRUCTION AREAS AND OTHER LAND DISTURBANCES:
   A.   Short term control measures may include:
      1.   Regularly scheduled wet suppression;
      2.   Dust suppressants applied in amounts and rates recommended by the manufacturer and maintained as recommended by the manufacturer;
      3.   Upwind temporary windbreaks, including fabric fences with the bottom of the fence sufficiently anchored to the ground to prevent material from blowing underneath the fence;
      4.   Starting construction upwind and stabilizing disturbed areas before disturbing additional areas; and/or
      5.   Stopping active operations during high wind periods.
   B.   Long term control measures may include:
      1.   Site stabilization using dust suppressants applied in amounts and rates recommended by the manufacturer and maintained as recommended by the manufacturer;
      2.   Reseeding using native grasses;
      3.   Xeriscaping;
      4.   Tree planting; and/or
      5.   Permanent perimeter and interior fencing. (Ord. 352, 2009)