§ 153.23 FINISHED CONSTRUCTION REQUIREMENTS.
   (A)   Upon the completion of construction, a FEMA elevation certificate, Form 81-31, which depicts all finished construction is required to be submitted to the Floodplain Administrator.
   (B)   If the project includes a floodproofing measure, then a FEMA floodproofing certificate, Form 81-65, is required to be submitted by the applicant to the Floodplain Administrator.
(Ord. 2014-05, passed 5-5-2014) Penalty, see § 10.99