(A) Temporary driveways will be allowed when the requirements for drainage and sight distance are met. The temporary driveway application shall be the same as a permanent driveway.
(B) The temporary driveway permit shall be limited to a maximum of 180 calendar days.
(C) The temporary driveway approach shall be constructed to support the type of vehicle/truck/equipment traffic expected. The minimum stone depth shall be six inches.
(D) A bond will be required with an amount equal to the cost of maintenance and repair of the existing infrastructure and the removal of the temporary driveway approach. The bond amount shall not be less than $1,000.
(E) Fees for a temporary driveway permit shall be the same as for a permanent driveway.
(Ord. 2005-11E, passed 11-28-05)