§ 50.50 SITE DEVELOPMENT PLAN; PLOT PLAN.
   (A)   A site development plan and area drainage map, which may include one or more lots, and containing the information required in this section, shall be submitted to the Planning Department to be routed to each department to be reviewed and/or Tech Committee for approval prior to the issuance of an improvement location permit.
   (B)   The site development plan shall show the following:
      (1)   The location of all existing and proposed buildings and driveway locations on the site or adjacent thereto;
      (2)   All existing or proposed roads, rights-of-way, building set-backs, drainage easements, and utility easements;
      (3)   The legal description and stamp by a licensed engineer and/or surveyor in the State of Indiana;
      (4)   The existing and proposed elevation, referenced to a known bench mark referenced to sea level datum. The high point of the public road adjacent to the property shall be set out; and
      (5)   The scale and north arrow.
      (6)   Site/location map with nearby road crossings (unless it is located in a platted subdivision).
      (7)   Flood zone and panel number.
      (8)   Show any designated wetland areas.
   (C)   The area drainage map shall show the following:
      (1)   The size and location of any regulated drain which will be affected by the proposed building. No permanent structure shall be erected within 75 feet, measured at right angles from the existing top edge of each bank of a regulated open drain, as determined by the County Surveyor, or the center line of a tiled regulated drain and show the easement distance on the plot plan;
      (2)   The size and location of an outlet, as defined in § 50.51, to which the water from the proposed building site will be taken;
      (3)   The location of the existing or proposed septic tank and disposal field;
      (4)   Cross-sections of open ditch outlets and invert elevations of tile outlets;
      (5)   The proposed location of tile, as required in § 50.51; and
      (6)   Show all erosion control measures including construction driveway entrance, silt fence, inlet protection, seeding, undisturbed areas, stockpile areas, and responsible individual and phone number.
(’86 Code, § 4-44) (Ord. 1995-12B, passed 12-11-95; Am. Ord. 2014-2A, passed 2-18-14)