[Amended 7-28-1986 by Ord. No. 17-1986; 4-24-1989 by Ord. No. 14-1989; 4-22-1996 by Ord. No. 3-1996; 8-24-2009 by Ord. No. 17-2009]
Site plan review fees shall be as follows:
A. Minor site plan:
(1) Application fee for preliminary and final minor site plan: $500.
(2) Escrow fee: $3,500. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.
B. Major site plan:
(1) Application fee for preliminary and final major site plan: $1,500.
(2) Escrow fee for preliminary site plan:
(a) New commercial and/or new industrial construction: $4,000 for the first acre of the gross area or fraction thereof, plus $800 for each additional acre or fraction thereof. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.
(b) Residential multifamily housing construction: $8,000 for two to 25 dwelling units, plus $50 per dwelling unit for every unit above 25. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.
(c) Building alteration: $2,500 for the first 3,000 square feet of gross floor area, plus $500 per 1,000 square feet of additional gross floor area or fraction thereof. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.
(3) Final escrow fees for major site plan:
(a) New commercial and/or new industrial construction: $2,500 for the first acre of the gross area or fraction thereof, plus $800 for each additional acre or fraction thereof. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.
(b) Residential multifamily housing construction: $8,000 for two to 25 units, plus $50 per dwelling unit for every unit above 25. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.
(c) Building alteration: $2,500 for the first 3,000 square feet of gross floor area, plus $500 per 1,000 square feet of additional floor area or fraction thereof. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.
C. Change of use.
(1) Application fee: $500.
(2) Escrow fee: $1,250. If escrow drops below 30% of the initial amount, the applicant must deposit funds to replenish escrow to 100% of initial amount deposited.