§ 51.21 PAVEMENT, CURB, AND SIDEWALK REPLACEMENT.
   The contractor shall restore or replace all of the appurtenances of the street, including, but not limited to, pavement, curb, and sidewalk. As soon as the trench has been backfilled, a temporary cold patch surface shall be placed and maintained for safe and comfortable public passage. The permanent surface must have a minimum of eight inches gravel, four inches bounded, broken stone, and two inches bituminous concrete, unless the pavement being replaced is of a higher degree of construction. In such case, the replacement must equal existing surface. Sidewalk and curb construction will be in accordance with the latest specifications and standards governing such construction.
(Ord. 235, adopted 9-4-84) Penalty, see § 51.99