§ 53.95 ENFORCEMENT ALTERNATIVES.
   When the authority determines that a violation of this chapter or any permit, or any damage to the authority’s collection system, is threatened or has occurred, one or more of the following actions may be taken:
   (A)   The authority may issue an order to cease and desist the violation and may direct the violator as follows:
      (1)   To comply either forthwith or in accordance with a time schedule set forth by the authority; or
      (2)   To take appropriate remedial preventive action in the event of a threatened violation.
   (B)   The authority may require the user in question to submit a detailed time schedule setting forth the specific proposed actions to prevent or correct a violation. The authority may issue an implementation schedule to the user, containing or modifying the specific actions and time schedule or requiring other actions within the time as the authority deems appropriate;
   (C)   The authority may issue an order directing the user to pay to the authority penalties and costs in accordance with § 53.94; and
   (D)   The authority may take direct enforcement action by filing suit in any court of competent jurisdiction pursuant to general laws or any other applicable statute or regulation.
(Ord. 9-1990, passed 7-1-1991)