(A) If a service pole is required it shall be furnished and installed by the customer at the customer’s expense upon approval by the Electric Utility. The meter base shall be furnished by the Electric Utility and installed by the customers electric contractor at the customers expense.
(B) A minimum 30-amp breaker box or fuse box shall be furnished by the customer at the customers expense and installed by the customers electric contractor at the customers expense and shall immediately follow the meter installation. Wire size shall not be less than number 6 copper.
(Ord. 7-1992, passed 12-21-1992) Penalty, see § 51.999