§ 97.06 PLANS AND SUBMITTALS.
   (A)   A lighting plan shall be required anytime exterior lighting is proposed, or modified except for one- and two-family dwellings. The lighting plan or plans with the required information and data shall be submitted to the city for review. The submission shall contain, but is not necessarily limited to the following:
      (1)   Plans indicating the location of all exterior lighting on the premises, and the type of illuminating devices, luminaries, lamps, supports, reflectors, and other devices;
      (2)   Description of the illuminating devices, luminaries, lamps, supports, reflectors, and other devices, and the description may include, but is not limited to properly identified catalog cut sheets by manufacturer and drawings (including sections where required) and height of luminaries, and
      (3)   Photometric plan and data sheets, such as that furnished by manufacturers, or similar to that furnished by manufacturers, indicating the angle of cutoff or light emissions.
   (B)   A licensed architect, licensed landscape architect, licensed electrical engineer or lighting certified designer shall prepare the plan and submittal. The submittal shall also contain a certification by the property owner or designated agent and the preparer of the plan that the lighting depicted on the plan complies with the requirements of this chapter when installed. Once the plan is approved by the city, the lighting installation shall conform to the approved plan and submittal.
   (C)   The above required plans, descriptions and data shall be sufficiently complete to enable the city to readily determine whether compliance with the requirements of this chapter will be secured. If such plans, descriptions and data cannot enable this ready determination, by reason of the nature of configuration of the devices, luminaries or lamps proposed, the applicant shall additionally submit as evidence of compliance to enable such determination such as certified reports of tests, provided that these tests shall have been performed and certified by a recognized testing laboratory.
   (D)   Should any luminary or type of light source be changed or substituted after the permit has been issued, a change request must be submitted to the city for approval, together with the adequate information to assure compliance with this chapter, which must be received and approved prior to the change or substitution.
(Ord. O-2008-025, passed 9-9-08)