941.05   PROCEDURES TO CONSTRUCT.
   Upon obtaining the Public Service Director's approval the person(s) wishing to construct a temporary treatment plant shall:
   (a)   Obtain from the Director the design criteria for the plant.
   (b)   Submit detailed plans, specifications and sufficient design information to allow proper evaluation of the plant's capacity to meet the design criteria.
   (c)   Obtain approval of the plans and specifications from Grove City, Ohio Environmental Protection Agency and all other governmental agencies having jurisdiction.
   (d)   Sign an agreement in such form and such terms as are required by the Director of Public Service and the Director of Law and post the necessary inspection deposit, bond, if required, and fees.
   (e)   Obtain written permission from the Director of Public Service to begin construction.
(Ord. C52-76. Passed 6-21-76.)