(A) For projects draining to and relying upon an existing detention facility or SCM for compliance with this chapter, the existing detention facility or SCM must be in compliance at the time of site plan or residential final plat approval unless a written plan of action to bring them into compliance is submitted to and approved by the Stormwater Administrator.
(B) No certificate of compliance or occupancy shall be issued without a final inspection and approval by the Stormwater Administrator of such existing SCMs or detention facilities, except where financial sureties have been submitted to and approved by the Stormwater Administrator to ensure compliance with this chapter.
(Ord. No. 24-021, § 1, passed 4-11-2024)