§ 153.0814 AS-BUILT DRAWINGS.
   (A)   Submittal. Prior to final inspection of the required improvements, the applicant shall submit to the Code Enforcement Officer one reproducible copy and two prints of as-built engineering drawings for each of the required improvements that have been completed. Each set of drawings shall be recertified by the applicant’s professional engineer, indicating the date when the as-built survey was made.
   (B)   Sewer and storm drainage. As-built drawings shall show the constructed vertical elevation, horizontal location and size of all sanitary and storm sewers, manholes, inlets, junction boxes, detention basins and other appurtenances or elements of the sewerage and storm drainage systems constructed to serve the subdivision. The subdivider shall cause all grading, excavations, open cutting and similar land surface disturbances to be mulched, seeded, sodded or otherwise protected. No work shall be initiated relative to the preparation of land or the installation of general improvements until such time as all aspects of the subdivider’s engineering plans and sedimentation control proposals have received approval.
   (C)   Water. As-built drawings shall depict water lines, valves, fire hydrants and other appurtenances or elements of the water distribution system constructed to serve the project. Such information shall include the horizontal location and size of water lines and the location and description of valves with dimensional ties.
   (D)   Sidewalks. As-built drawings shall depict the location with respect to the street right-of-way, width and vertical elevation.
   (E)   Control points. As-built drawings shall show all control points and monumentation.
(Ord. 3020, passed 9-10-2013, § 4.35.5)