Table 5 | ||||
Post-Construction Storm Water Management in New Development and Redevelopment | ||||
Develop, implement, and enforce a program to address storm water runoff from new development and redevelopment projects that disturb greater than or equal to one acre, in accordance with 3.2.5.1.1 of the Ohio General Permit. | ||||
BMP | Measurable Goal | Time | Responsible Party | Rationale |
Develop standard process of reviewing plans, etc. | Develop standardized process for reviewing plans by multi- departmental staffs | Start date: PCD + 6 months End date: PCD + 18 months Duration: | Greenville | To be the most efficient in reviewing plans |
Continue to enforce requirement of etention/detention of storm water | Review ordinance to ensure requirements are sufficient and understandable | Start date: PCD + 3 months End date: PCD + 60 months Duration: | Greenville | To minimize high rate of discharge of storm water during most rain events; to minimize erosion and discharge of sediments |
Develop and implement strategies which include a combination of structural and/or non-structural BMPs, in accordance with 3.2.5.1.2 of Ohio's General Permit. | ||||
BMP | Measurable Goal | Time | Responsible Party | Rationale |
Review and update planning requirements per City's Comprehensive Plan | Amend ordinances if necessary to reflect updated comprehensive plan land use requirements | Start date: PCD + 6 months End date: PCD + 27 months Duration: | Greenville | To align land use requirements with ordinance-based controls |
Use a regulatory mechanism to address post-construction runoff from new development or redevelopment projects, in accordance with 3.2.5.1.3 of Ohio's General Permit | ||||
BMP | Measurable Goal | Time | Responsible Party | Rationale |
Review ordinance requiring retention/detention area maintenance responsibilities | Determine if ordinances meet expectations of having retention/detention areas maintained by homeowners or City | Start date: PCD + 3 months End date: PCD + 39 months Duration: | Greenville | To determine if enforcement of maintenance needs to be improved or changed via ordinance changes |
Ensure adequate and long-term operation and maintenance of BMPs, in accordance with 3.2.5.1.4 | ||||
BMP | Measurable Goal | Time | Responsible Party | Rationale |
Consider adopting an alternative funding source via developing storm water fee | Complete study to determine if new revenue via storm water fee is needed to fully implement program | Start date: PCD + 3 months End date: PCD + 39 months Duration: | Greenville | Added funding may be required to fully implement Phase II requirements. Creating new funding source would free up current funding for other projects in City's GF |
(Ord. 07-04. Passed 1-23-07.)