1470.40 PROGRAM OVERVIEW.
 
Table 4
Construction Site Storm Water Runoff Control
Create an ordinance or other regulation requiring erosion and sediment controls on disturbed sites equal to or greater than one acre that includes sanctions to help ensure compliance, in accordance with 3.2.4.1.1 of Ohio's General Permit.
BMP
Measurable Goal
Time
Responsible Party
Rationale
Review and amend ordinance regarding sediment and erosion control
Review ordinance by September 2004 and update if necessary to meet regulatory requirements
Start date: PCD + 4 months
End date: PCD + 21 months
Duration:
Greenville
To add language that complies with required minimums
 
Require construction site operators to implement appropriate erosion and sediment control BMPs, in accordance with 3.2.4.1.2 of Ohio's General Permit.
BMP
Measurable Goal
Time
Responsible Party
Rationale
Review and amend ordinance regarding appropriate BMPs for construction site erosion and sediment control
Review and amend ordinance to list acceptable controls for erosion and sediment controls
Start date: PCD + 4 months
End date: PCD + 27 months
Duration:
Greenville
To add language that complies with required minimums
Require construction site operators to control waste, including discarded building materials, concrete truck washout, chemicals, litter, and sanitary waste, in accordance with 3.2.4.1.3 of Ohio's General Permit.
BMP
Measurable Goal
Time
Responsible Party
Rationale
Review and amend ordinance regarding the control of site-generated waste
Review and amend ordinance to control construction site waste disposal practices
Start date: PCD + 4 months
End date: PCD + 27 months
Duration:
Greenville
To add language that complies with required minimums
Develop and implement procedures for site plan review which incorporates consideration of potential water quality impacts, in accordance with 3.2.4.1.4 of Ohio's General Permit.
BMP
Measurable Goal
Time
Responsible Party
Rationale
Review and amend ordinance regarding site plan review procedure
Review ordinance and procedures dealing with site plan review process
Start date: PCD + 4 months
End date: PCD + 21 months
Duration:
Greenville
To add language that complies with required minimums
Develop and implement procedures for receipt and consideration of information submitted by the public, in accordance with 3.2.4.1.5 of Ohio's General Permit.
BMP
Measurable Goal
Time
Responsible Party
Rationale
Review public involvement procedures
Review current public involvement procedures to ensure public is aware of construction site maintenance requirements
Start date: PCD + 6 months
End date: PCD + 21 months
Duration:
Greenville
To ensure public is aware of potential water quality issues
Develop and implement procedures for site inspection and enforcement of control measures, in accordance with 3.2.4.1.6 of Ohio's General Permit.
BMP
Measurable Goal
Time
Responsible Party
Rationale
Develop standard site inspection procedures and form
Develop a standardized site inspection/record form for use by City staff during routine daily activities to log site compliance with requirements
Start date: PCD + 12 months
End date: PCD + 24 months
Duration:
Greenville
Multiple site visits by different staff will help long-term controls
 
(Ord. 07-04. Passed 1-23-07.)