(A) The generator shall be installed on a four-inch thick concrete slab near the lift station electrical panels. The concrete pad shall be sized so as to include access to the controller and to other maintenance-related parts.
(B) The manufacturer or his or her representative shall provide start-up and testing services to ensure proper installation and operation of the generator. The start-up services shall be coordinated with the town and be witnessed by appropriate town personnel.
(Ord. 2010-3, passed 10-6-2010)