The company will proceed as follows pursuant to Federal Communications Commission’s regulations:
(A) Apply for all necessary grants or waivers within 90 days of the issuance of the franchise;
(B) Apply for pole attachment agreements with the appropriate companies within 30 days after the issuance of the franchise;
(C) Submit to the city detailed system layout plans within six months after obtaining the necessary pole attachment agreements;
(D) Begin construction within 30 days after written approval by the city on system layout plans and receipt of a certificate of compliance from the Federal Communications Commission;
(E) Render service to customers in the first section no later than six months after the commencement of construction; and
(F) Render service to all feasible areas within the city within 24 months after commencement of construction.
(Ord. 1973-16, passed 8-24-1973) Penalty, see § 10.99