When required, the Inspections Department shall make at least, but not limited to, the following inspections of all work being performed under the permit and shall either approve that portion of the construction as completed or shall notify the permit holder or his agent wherein the same fails to comply with the law. It shall be the responsibility of the permit holder or his agent to give timely notice to the Inspections Department when the work for these inspections is ready and to schedule the applicable inspection or re-inspection.
(A) Footing inspection. To be made after the trenches are excavated, all grade stakes are installed, all reinforcing steel supports are in place, and appropriately tied, all necessary forms are in place and braced and before any concrete is placed.
(B) Pre under slab inspection. To be made after all forms have been placed, all electrical, plumbing and/or heating and air conditioning facilities, all crushed stone, a vapor barrier, all reinforcing steel with supports and tied and/or welded wire fabric is installed when required but before any concrete is placed.
(C) Foundation and pre sub-floor inspection. To be made after all foundation supports and floor joist are installed.
(D) Frame inspection and rough in. To be made after the roof, all framing, fireblocking, and bracing is in place and all pipes, chimneys, vents, electrical panel, electrical wire, receptacle boxes, fixture boxes, plumbing pipes, heat and air conditioning vents and all other items in place which will be covered by insulation or interior finishes.
(E) Insulation inspection. To be made after rough-ins are complete with insulation being installed and prior to finish being applied.
(F) Final inspection. To be made after the building or structure is completed and ready for occupancy.
(Ord. passed 6-21-21)