§ 152.089  GENERAL REGULATIONS.
   (A)   No developer shall proceed with the construction of any utilities or improvements or make connection to any existing township facility or utility system without proper inspection by an authorized official or representative thereof. Drawings and specifications shall be provided in sufficient detail to show the form, construction and method of installation of the following and shall accompany or otherwise be a part of the subdivision plan:
      (1)   Streets, gutters and culverts;
      (2)   Storm sewers and surface drainage facilities;
      (3)   Water system;
      (4)   Sanitary sewers and septic tanks; and
      (5)   Survey monuments.
   (B)   No person shall dig or make any cuts or changes whatsoever in the cartway, gutters or rights-of-way of any township, county or state road without first obtaining required approvals and/or permits.
   (C)   No person shall connect to any water line, storm or sanitary sewer without obtaining a permit and paying the proper connection charge.
   (D)   Grade stakes shall be set and cut sheets prepared and a copy furnished to the Township Administrative Secretary/Treasurer and Township Engineer before any work is started.
   (E)   The developer shall notify the Township Engineer at least 24 hours prior to his or her intention to proceed with the construction or installation of said streets and improvements or any other work related to the improvements.
(2003 Code, § 146-27)  (Ord. 2-96, passed 7-5-1996)