(A) Applications. The following applications may be filed:
(1) Exempt subdivision;
(2) Minor subdivision;
(3) Major subdivision;
(4) Preliminary approval; and
(5) Final approval.
(C) Action on applications.
(1) All applications for approval of a plat, whether preliminary or final, shall be acted upon by the Township Supervisors not later than 90 days following the date of the regular meeting of the Planning Commission next following the date the application is filed; provided that, should the said next regular meeting occur more than 30 days following the filing of the application, the said 90-day period shall be measured from the thirtieth day following the day the application has been filed.
(2) The decision of the Supervisors shall be in writing and shall be communicated by the Township Administrative Secretary/Treasurer to the applicant personally or mailed to him or her at his or her last known address not later than 15 days following the decision.
(3) When the application is not approved in terms as filed, the decision shall specify the defects found in the application and describe the requirements which have not been met and shall, in each case, cite the provisions of the statute or ordinance relied upon.
(4) If the Planning Commission requests additional data or plan changes as conditions precedent to approval, the subdivider may, in lieu of having a disapproval or conditional approval sent to the governing body, request another review meeting to provide the requested documentation. The subdivider shall submit the request to the Planning Commission in writing within five working days (Monday through Friday, holidays excluded) of the initial review meeting and shall further agree in writing to an extension of the original 90-day review period, if requested by the Planning Commission.
(2003 Code, § 146-12) (Ord. 2-96, passed 7-5-1996)