Loading...
A permit shall be obtained before beginning construction, alteration, or repair of any building or structure, the cost of which exceeds $500, using forms furnished by the Building Inspector, and all fees required by this code shall be paid to Clerk-Treasurer.
(Ord. 14-1996, passed 8-14-1996) Penalty, see § 10.99
All work done under any permit shall be in full compliance with all other ordinances pertaining thereto, and in addition to the fees for permits, there shall be paid the fees prescribed in the ordinances.
(Ord. 14-1996, passed 8-14-1996) Penalty, see § 10.99
The fees for the permit and inspections of all construction, alteration, or repair of any building or structure shall be as follows:
Residential Permit Fee Schedule
| ||
Fee
|
Residential Permit Fee Schedule
| ||
Fee
| ||
One Family Dwelling. 2,000 sq. ft or larger $.18 per sq. ft. (includes garage). If basement is finished, it will be included in square footage. | $350 | |
Two Family Dwelling. 2,500 sq. ft. or larger $.18 per sq. ft. (includes garage). If basement is finished, it will be included in square footage. | $500 | |
Modular Residence. | $150 | |
Second floor finish on site | $75 | |
Manufactured residence | $100 | |
Single wide Double wide | $150 | |
Additions and alterations | $150 | |
$2,000 sq. ft or larger $.18 per sq. ft. (includes garage). Electric service extra fee. | $50 | |
Detached garage | $50 | |
Electric service fee | ||
Accessory building | $75 | |
Pole building, shed, etc. | $50 | |
Poured foundation extra fee | $50 | |
Electric service extra fee | ||
Swimming pools | $50 | |
Above ground | $150 | |
In-ground | ||
Electric service | $50 | |
Gas service | $50 | |
Foundation release | $50 | |
Re-inspection | $50 | |
Temporary occupancy permit | $50 | |
Commercial Permit Fee Schedule | ||
Up Front | Unit Price |
Commercial Permit Fee Schedule | ||
Up Front | Unit Price | |
Apartments | $300 | $.20 sq. ft. |
Condominiums | $300 | $.20 sq. ft. |
Townhouses | $300 | $.20 sq. ft. |
Hotels-motels | $500 | $.20 sq. ft. |
Assembly | $400 | $.20 sq. ft. |
Business | $400 | $.22 sq. ft. |
Educational | $600 | $.22 sq. ft. |
Factory and industrial | $500 | $.18 sq. ft. |
Institutional | $600 | $.24 sq. ft. |
Storage | $300 | $.10 sq. ft. |
Utility and miscellaneous | $200 | $.15 sq. ft. |
Elevators | $200 | $50 per floor |
Communications facility | $400 | $14 sq. ft. lin. ft. |
Sign | $200 | $.10 sq. ft. |
Interior build-out | $150 | $.20 sq. ft. |
Re-roofing | $100 | $.03 sq. ft. |
Temporary structures, tents, etc. | $50 | $10 each |
Retaining walls-over 4 ft. high | $75 | $1 lin. ft. |
Inside fire suppression systems | $150 | $.03 sq. ft. |
Hood and suppression systems | $150 | $10 lin. ft. |
Fire alarms | $100 | $.015 sq. ft. |
Electric service | $100 | $10 per meter |
Gas service per meter | $100 | $5 per meter |
Foundation release | $300 | |
Re-inspection fee | $50 | |
Temporary occupancy permit - to be paid up front | $100 | |
Unspecified permit fee - for any permit type not specifically listed in this fee schedule, the fee shall be calculated to the most similar permit type, which is to be determined at the discretion of the Building Commissioner | ||
(Ord. 7-1996, passed 5-15-1996; Ord. 14-1996, passed 8-14-1996; Ord. 2012-17, passed 12-26-2012)
Loading...