§ 154.188 PLANNING COMMISSION REVIEW OF SITE PLAN.
   Upon receipt of a complete site plan from the Clerk, the Planning Commission shall undertake a study of the same and shall, within 45 days, arrive at a decision concerning such site plan. If either major deficiencies are found during this review or an incomplete site plan has been submitted, or changes or modifications in the proposed site plan are needed to achieve conformity to the standards in this chapter, the applicant will be notified of these in writing. Upon receipt of a revised plan from the applicant, the applicant will be placed on the next available agenda (or that of a special meeting if the applicant makes such a request). The Planning Commission may extend this time for periods not to exceed 31 days each if such extensions are necessary for adequate review.
(Ord. passed 12-30-2000 , § 5.2.3)