§ 151.064 EXPIRATION OF PERMIT.
   (A)   If the work described in any permit has not begun or has not been completed within six months from the date of issuance thereof, the permit shall expire and the applicant shall have to reapply for another permit. It is expected that all new construction be completed within six months.
   (B)   In the case of new construction, which may reasonably be expected to require more than six months for completion, the city may specify a time limit in excess of six months at the time of original issuance of the building permit on a case-by-case basis, and shall extend the time limit accordingly.
(1985 Code, Art. IV, § 405) (Ord. 99-005, passed 4-13-1999)