§ 151.21(2) PERMIT REQUIREMENTS.
   The floodplain development permit and/or the building permit shall include, but not be limited to:
   (A)   A complete description of all the development to be permitted under the floodplain development permit (for example, house, garage, pool, septic, bulkhead, cabana, pier, bridge, mining, dredging, filling, grading, paving, excavation or drilling operations, or storage of equipment or materials, and the like).
   (B)   The Special Flood Hazard Area determination for the proposed development with available data specified in § 151.07.
   (C)   The Regulatory Flood Protection Elevation required for the reference level and all attendant utilities.
   (D)   The Regulatory Flood Protection Elevation required for the protection of all public utilities.
   (E)   All certification submittal requirements with timelines.
   (F)   A statement that no fill material or other development shall encroach into the floodway or non-encroachment area of any watercourse unless the requirements of § 151.35 have been met.
   (G)   The flood openings requirements, if in Zones A, AE, AH, AO, or A99.
   (H)   Limitations of below BFE enclosure uses (for example, parking, building access and limited storage only), if applicable.
(Ord. 2018-24, passed 5-21-18)