(a) Upon a showing of good cause, the Zoning Administrator may grant a request by a Wind Energy Turbine's owner(s) or operator(s) for a reasonable extension of time to complete decommissioning as required by Section 1333.07.
(b) When a Wind Energy Turbine's owner(s) or operator(s) fail to complete
decommissioning pursuant to Section 1333.07, the Zoning Administrator is authorized to designate a contractor to complete decommissioning with the expense thereof to be charged to the violator or to become a lien against the premises.
(Ord. 23-2010. Passed 1-6-11.)