§ 153.35  AS-BUILT REQUIREMENTS.
   Prior to issuance of a use and occupancy permit or final release of bond, the as-built condition of critical storm water management facilities must be reviewed and approved.
   (A)   The volume, capacity, slope, configuration, condition, “as-planted” plans and topographic information, as well as all pipe size, material, lengths, for all detention, retention, and water quality practices shall be certified by a professional engineer licensed in the state. This information shall be provided to the town in the form of an as-built drawing or other electronic form accepted/required by the town. The as-built certification shall indicate if final conditions are consistent with, or exceed, the storm water quality management permit provisions.
   (B)   If it is determined that information provided in the as-built drawing, certification, inspection, or survey of the site do not meet or exceed the storm water quality management permit requirements, the town reserves the right to withhold certification of occupancy or final bond. Furthermore, other enforcement mechanisms, as identified within this subchapter, may be applied to the person certifying the as-built information.
   (C)   If upon inspection by the town it is determined that there is an item that must be addressed to receive acceptance of site conditions, then the person shall be required to continue inspections and maintenance as described in the storm water quality management permit.
(Ord. G-12-02, passed 1-17-2012)