1175.06 PERMIT APPLICATIONS; AUTHORITY OF BUILDING OFFICIAL AND PLANNING AND ZONING COMMISSION.
   All applications for Protected Hillside Zone permits shall be submitted to the Building Official. The Building Official shall prepare forms necessary for such applications. The Building Official shall review the application to ensure that the application contains the information required by Section 1175.07. In connection with such review, the Building Official is authorized to consult and obtain opinions from such other professionals as the Village Engineer, hydrological and geotechnical engineers, botanists, biologists and landscape architects as he or she may deem necessary. No Protected Hillside Zone permit shall be issued until the application, together with the report of the Building Official, has been reviewed and approved by the Planning and Zoning Commission.
(Ord. 2508. Passed 9-8-92; Ord. 2014-03. Passed 4-8-14.)